Day 1 (10/18/21)
- Mark Centers
- Layout Design
- Make Oak Pegs
- Drill Holes in Footings
- Cut All Thread for Post Supports
- Install Post Supports (epoxy in place)
- Start Cutting Knees and Making Knee Tenons
- Start Post Mortices
|
|
Day 2 (10/19/21)
- Continue to Layout Design
- Finish Making Knees
- Cut Notches and Mortices in Posts
- Start Cutting Mortices in Beams
|
|
Day 3 (10/20/21)
- Match Knees to Posts - Clean up Mortices and Tenons
- Cut Mortices in Beams
- Cut Beams to Match Each Other
- Fit Knees to Beams
|
|
Day 4 (10/21/21)
- Lay Out Ends on Driveway
- Use Lift to Pick up the Big Parts
- Install Ends on Footings
- Install Tie Beams
- Cut Rafters
- Start Pegging Joints
- Pops, Liz and Chuck Come to Join the Party
|
|
Day 5 (10/22/21)
- Clean Up Some Joints
- Finish Pegging Joints
- Install Rafters
- Clean Up
|
|
|